On 17 July 2023, the Office of the President officially announced the President’s Order on the Law on Tendering No. 22/2023/QH15 passed by the 15th National Assembly at the fifth Session (“Law on Tendering 2023”). Accordingly, the Law on Tendering 2023 contains adjustments to the scope and subjects of the law, as well as amendments to the process and procedures for selecting contractors and investors and promoting the application of online tendering. Additionally, the Law on Tendering 2023 adds many new regulations to remove problems with Tendering in the medical field.

In this article, CNC analyzes some important new points of the Law on Tendering 2023 compared to the Law on Tendering No. 43/2013/QH13 (“Law on Tendering 2013”).

The scope of the Law on Tendering 2023 is both narrowed and expanded

Compared to the Law on Tendering 2013, the Law on Tendering 2023 changes the scope of law regarding projects on development investment financed by state-owned enterprises. Specifically, according to the Law on Tendering 2013, projects financed by state-owned enterprises with a level equal to 30% or more, or less than 30% but more than 500 billion VND in total investment of the project must go through the Tendering process [1].

Nevertheless, the Law on Tendering 2023 shall be applied to projects on investment of state-owned enterprises (which means 100% of the project’s funds shall be arranged by the state-owned enterprises), besides, projects of enterprises that have 100% of its charter capital to be owned by state-owned enterprises shall fall within the scope of the Law on Tendering 2023 [2].

Supplementing some cases of direct appointment and competitive quotation

Compared to the Law on Tendering 2013, the Law on Tendering 2023 supplements some cases of direct appointment and competitive quotation.

Most notably, direct appointment applies to:

  • Packages for the procurement of drugs, chemicals, test equipment, medical devices, spare parts, and accessories used in providing emergency aid to patients as prescribed in the Law on Medical Examination and Treatment whenever health facilities lack such drugs, chemicals, test equipment, medical devices, spare parts, accessories; packages for procurement of drugs or medical devices which can be manufactured by the only one manufacturer in the market [3];
  • Consulting service packages for preparation of construction planning which are designated to the authors of construction planning schemes or initiatives that have been successful in the construction planning competition [4];
  • Packages for which there is only one contractor capable of performing the contract in the market due to specific technological solution requirements [5];
  • Packages of nationally important projects eligible for direct appointment according to the National Assembly’s resolutions issued when deciding investment guidelines [6].

The competitive quotation method is applied to procurement and construction packages whose price does not exceed 5 billion VND, as well as their construction parts have already obtained approved for construction drawings designs [7].

Decentralizing the authority to determine the contractor selection method in special circumstances

According to the Law on Tendering 2013, the Prime Minister directly checks and determines the contractor and investor selection method in all special circumstances. However, the Law on Tendering 2023 amends this regulation and decentralizes the authority to manage the method applied to contractor selection cases to other authorities besides the Prime Minister [8]:

Supplementing some types of contracts used in contractor selection

In addition to lump sum contracts, fixed unit price contracts, adjustable unit price contracts, and time-based contracts, the Law on Tendering 2023 includes some other types of contracts as indicated below[9]:

  • Cost plus fee contracts;
  • Performance-based contracts;
  • Percentage-based contracts;
  • Mixed contracts.

The cost plus fee and mixed contracts are two types of contracts prescribed in the Law on Construction 2014 [10], however, neither have been regulated in the Law on Tendering 2013.

Features of the aforementioned contracts:

In addition to tender security, the Law on Tendering 2023 removes escrow and supplements a new measure – a tender bond insurance certificate issued by a domestic non-life insurer or branch of a foreign non-life insurer duly established under the law of Vietnam (“insurance company”) [11]. Accordingly, the insurance company (the guarantor) will utilize their financial capacity and reputation to commit in writing to the (the beneficiary) that the insurance company’s client (the guarantee) must fulfil the contract’s obligations, otherwise, the insurance company will perform the financial obligation on behalf of the guarantee.

In essence, the tender bond insurance is quite similar to a bank guarantee, however, the guarantor in this case will be an insurance company (instead of a credit institution or foreign bank branch as in a bank guarantee).

Supplementing the investor selection method

According to the Law on Tendering 2013, the method of selecting an investor includes: (i) One-phase: Single Envelope Tendering Procedure and (ii) One-phase: Dual Envelope Tendering Procedure.

The Law on Tendering 2023 adds the Two-phase: Single Envelope Tendering Procedure which is applied to open tendering for investment projects which have specific sectoral, regional, or local socio-economic development requirements but of which specific technical, social, economic, and environmental standards are not yet determined [12].

The process and procedure for selecting the investor, in this case, is instructed by the Decree on detailed guidance on some articles and the way to perform the Law on Tendering for investor selection. According to the first draft of this Decree (promulgated along with Document No. 7254/BKHDT-QLDT dated 5 September 2023 by the Ministry of Planning and Investment), the process and procedure to select the investor using the Two-phase: Dual Envelop Procedure is as follows:

Eliminating the regulation on selecting the investor in special circumstances

The Law on Tendering 2023 eliminates the regulation on investor selection as prescribed in Article 26 of the Law on Tendering 2013. One of the reasons for removing this regulation is because the latest draft being prepared for submission to the National Assembly, the Land Law 2023, will also regulate the issue of tendering to select investors to implement projects using land, however, there are no regulations on tendering to select investors in special cases.

Hence, eliminating the case of selecting investors in special circumstances ensures the consistency between the Law on Land and the Law on Tendering.

Regulating in detail the investment project contract signed with the investor

In the Law on Tendering 2023, issues relating to the contract between state authorities and selected investors (“investment project contract” in accordance with the Law on Tendering 2023) are regulated in detail and clearly. Accordingly, Article 73 of the Law on Tendering 2023 outlines the basic contents of the investment project contract, including:

  • Contractual parties’ information;
  • Investment project information;
  • Responsibility to compensate and manage relocation procedures and organize construction of auxiliary works (if any); allocation or lease of land (if any);
  • The investor’s obligations to fulfil commitments proposed in their tender; establishment of an enterprise in charge of managing the investment project (if any);
  • Performance security; rules and conditions for modification and termination of contract; transfer of rights and obligations by the parties;
  • Governing law and dispute settlement mechanism.

The contents of the investment project contract must be guided in detail in Appendix II of the first draft of the Decree on detailed guidance on investor selection.

In addition, Article 74 of the Law on Tendering 2023 stipulates in detail that the duration of the investment project contract must be counted from the date that the contract takes effect to the date the investor fulfils its proposed undertakings in the tender submission and other obligations under the parties’ agreement in the investment project contract. When the contract expires, the investor must perform the investment project in compliance with the laws on investment and related laws.

With respect to the measures for ensuring the obligation to perform the contract of the investor, similar to the provisions applied to the contract signing with the contractor, the Law on Tendering 2023 eliminates escrow from the list of measures, and instead adds the requirement of a guarantee insurance certificate.

In addition, the Law on Tendering 2023 specifically stipulates that in the event that an investor transfers an investment project, the parties can amend the investment project contract, rather than sign a new contract with the investor receiving the project.

Some changes in the way of submitting petition in tendering

If the Law on Tendering 2013 only allows contractors and investors to be the subject of petitions submitted in tendering, the Law on Tendering 2023 broadens the scope of subjects to have this type of right. Specifically, authorities or organizations having an interest in the package or investment project maintain the right to submit petitions regarding the tender documents [13].

Additionally, the content of the petition under the Law on Tendering 2023 is also amended. Specifically, the Law on Tendering 2013 allows contractors and investors to submit petitions relative to the contractor or investor selection result. Meanwhile, the Law on Tendering 2023 narrows the scope of the petition, accordingly, the contractor or the investor can only submit a petition relating to the result of evaluating the tender submission of such petitioning investor or contractor [14].

Tightening the provision on prohibited acts in tendering

With respect to prohibited acts in tendering, the Law on Tendering 2023 provides stricter provisions. Specifically:

Firstly, regarding Collusive practice, the Law on Tendering 2013 primarily focuses on the expression “agreement” (for example, reaching an agreement of withdrawing from Tendering or withdrawing the tender submission previously submitted allowing one party or more in the agreement win the tender or agreeing to let one or many parties prepare a tender submission for the tendering parties so that one party may win the tender) [15].  However, the Law on Tendering 2023 broadens the scope of collusive practices, accordingly, if the parties “arrange”, or “coerce” a party or parties to withdraw the tender dossier for one party to win the tender or without agreement but deliberately refuses to perform an obligation to facilitate one party to win the tender, these practices are considered collusion [16].

Secondly, regarding Fraudulent practice, the Law on Tendering 2023 does not consider situations in which “Individuals who directly assess the EOI (Expression of Interest) responses, Applications, Tender Submission, Proposals, evaluate the result of selection of shortlist, result of selection of investor, contractor, intentionally providing erroneous reports or false information falsifying the result of selection of contractors/investors” as prescribed in point b Article 89.4 of the Law on Tendering 2013 as a fraudulent act [17]. Besides, the act of “Forging or falsifying information of a dossier or document in tendering” is considered a Fraudulent act [18] without any pecuniary or miscellaneous interest or aim to avoid any obligation as required in the Law on Tendering 2013.

Thirdly, regarding Interference practice in tendering, in addition to cases as prescribed by the Law on Tendering 2013, the Law on Tendering 2023 broadens the scope of prohibition on interference relative to (i) the act of selecting contractors, and investors; (ii) tendering and (iii) online tendering [19].

Fourthly, regarding Inequality and non-transparency, the Law on Tendering 2023 broadens the scope of familial relationships between the tenderer and the individual of the party calling for tenders or competent authority, the head of the employer, or the party calling tenders compared to the Law on Tendering 2013 [20]. Accordingly, the Law on Tendering 2023 does not itemize the cases in which the tender is considered to be in a familial relationship with the party calling for tenders, instead, the Law 2023 references the definition of a familial relationship in the current Law of Enterprise.

Further, according to the Law on Tendering 2013, if the individual named in the tender submission has worked at the entity, calling for tenders, for 12 months, then the act of submitting a tender dossier for this entity is considered inequality and non-transparency [21]. Meanwhile, according to the Law on Tendering 2023, this practice only constitutes inequality and non-transparency when the tenderer has worked at the entity calling for tenders and held an executive or managerial position [22].

Download PDF here: [PDF] 09 NEW POINTS OF THE LAW ON TENDERING 2023

————————————————-

[1] Clause 2, Article 1 the Law on Tendering 2013.

[2] Point a, clause 2 Article 2 the Law on Tendering 2023.

[3] Point c, clause 1, Article 23 the Law on Tendering 2023.

[4] Point g, clause 1, Article 23 the Law on Tendering 2023.

[5] Point i, clause 1, Article 23 the Law on Tendering 2023.

[6] Point k, clause 1, Article 23 the Law on Tendering 2023.

[7] Clause 4, Article 24 the Law on Tendering 2023.

[8] Clause 2, Article 29 the Law on Tendering 2023.

[9] Clause 5, 6, 7, 8 Article 64 the Law on Tendering 2023.

[10] Point dd, clause 3, Article 140 and point e, clause 3, Article 140 the Law on Construction 2014.

[11] Clause 1, Article 14 the Law on Tendering 2023.

[12] Clause 3, Article 35 the Law on Tendering 2023.

[13] Point a clause 1 Article 90 the Law on Tendering 2023.

[14] Point a clause 1 Article 90 the Law on Tendering 2023.

[15] Clause 3 Article 89 the Law on Tendering 2013.

[16] Clause 3 Article 16 the Law on Tendering 2023.

[17] Clause 4 Article 16 the Law on Tendering 2023.

[18] Point a clause 4 Article 16 the Law on Tendering 2023.

[19] Clause 5 Article 16 the Law on Tendering 2023.

[20] Clause 6 Article 16 the Law on Tendering 2023.

[21] Point e clause 6 Article 89 the Law on Tendering 2023.

[22] Point e clause 6 Article 16 the Law on Tendering 2023.

 

liên hệ
Công ty Luật TNHH CNC Việt Nam

    CNC© | A Boutique Property Law Firm

    The Sun Avenue, 28 Mai Chí Thọ, Phường An Phú, Quận 2,

    Tp. Hồ Chí Minh, Việt Nam

    T: (+84-28) 6276 9900 | H/L: (+84) 916 545 618

    cnccounsel.com | contact@cnccounsel.com

    cnclicense.com

    hopdongmau.net

    Content Protection by DMCA.com

    Trả lời

    This site uses Akismet to reduce spam. Learn how your comment data is processed.